Dukes Park and East Anglia ONE

My inbox has been buzzing with anxious emails this week  from people worried about a possible planning application for land adjoining Dukes Park. Although planning is a District Council issue it is in Woodbridge County division,and  is  also the site through which the EA One underground high tension cabling is due to be routed. As this appeared to have slipped under the radar of both residents and district council until I raised it last Monday,  I contacted the EA ONE  link officer at Suffolk County Council. I wanted to know if he had definitive information on the separation necessary between  housing development and underground high tension cables. closeup EA1

Here is his brief resume of the status quo and implications as he sees it:

East Anglia ONE have acquired both permanent and temporary rights for land within the Order Limits (red line boundary). The exact location of these rights however would not be determined until the project is being built, because the final positioning of the cables is not known. What we know now is that the corridor depicted on the plans is generally 75m wide though only 55m is needed for construction and this could lie anywhere within the 75m swathe. The final footprint for the operational development will be 42m The rights that have been acquired are set out within Schedule 6 of the Development Consent Order  . The permanent rights within the cable corridor generally provide for the retention of cables/ducts together with a surface right of access for occasional maintenance. Lands subject to temporary rights (i.e the ‘surplus’ 33m) would be returned to the current owner post construction (that is, around 2020). However as the SCC link officer understands it:

“…restrictive covenants are also in place. Activities within the Order Limits are prohibited as below. The footprint of the land these rights cover would diminish from the construction (75m) to operational phase (42m), but as I understand it apply to the full 75m currently: (a) prevent anything to be done in or upon the Order land or any part thereof for the purpose of the erection of any buildings or construction erection or works of any kind (including the foundations or footings thereto); (b) prevent anything to be done by way of hard surfacing of the Order land with concrete of any kind or with any other material or surface whatsoever without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed if the proposed surfacing would not cause damage to relevant part of the authorised project nor make it materially more difficult or expensive to maintain the authorised project); (c) prevent anything to be done by way of excavation of any kind in the Order land nor any activities which increase or decrease ground cover or soil levels in any manner whatsoever without the consent in writing of the undertaker save as are reasonably required for agricultural activities or are required to be carried out by National Grid in order to exercise their rights in relation to their apparatus within the Order land; (d) prevent the planting or growing within the Order land of any trees, shrubs or underwood without the consent in writing of the undertaker (such consent not to be unreasonably withheld or delayed provided that the proposed trees, shrubs or underwood would not cause damage to the relevant part of the authorised project nor make it materially more difficult or expensive to access the relevant part of the authorised project). Consequently very little can happen within the area covered by the Order Limits at the moment. The extent of that redline boundary will shrink in due course, but even in that remaining area, no buildings could erected.”

The officer points out that land outside the Order Limits, and any land used during construction once returned to its original owner is not subject to any East Anglia ONE restrictive covenants. However it would be  on each side of the cabling  area. Requests for any further specific elucidation  are probably best directed to:

Joanna Young,  Stakeholder Manager ScottishPower Renewables East Anglia Offshore Wind, Room 101, OrbisEnergy, Wilde Street, Lowestoft, Suffolk, NR32 1XH. jyoung@scottishpower.com

Be Sociable, Share!